Introduction
Location And Access
Catchment Area:
Dam Site:
VDC lies in Catchment Area:
Dam Site:
Silence features
|
1.
Reservoir |
|
|
Full
Supply Level (FSL) |
El.
540 masl |
|
Maximum
Flood Water Level |
El.
542 masl |
|
Reservoir
upper boundary incl. 3m freeboard |
El.
545 masl |
|
Minimum
Operating Level (MOL) |
El.
496 masl |
|
Minimum
Operating Level Ultimate (MOL.ult.) |
El.
467 masl |
|
Minimum
Reservoir Level (MRL) |
El.
440 masl |
|
Reservoir
Bottom Level |
El.
326 masl |
|
Gross
Capacity (at FSL) |
4
467 Mm3 |
|
Active
storage between FSL and MOL |
2
226 Mm3 |
|
Reserve
Live Storage between MOL and MOL.ult. |
952
Mm3 |
|
Conservation
volume between MOL.ult. and MRL |
582
Mm3 |
|
Dead
Storage between MRL and reservoir bottom |
708
Mm3 |
|
Surface
Area (at FSL) |
63
km² |
|
Surface
Area (at MOL) |
39
km2 |
|
2.
Hydrology |
|
|
Catchment
Area |
5
005 km2 |
|
Long
Term Average Flow |
222
m3/s (see note at the end of this table) |
|
Construction
Flood (20 years) |
3
070 m3/s |
|
Design
Flood Discharge (10 000 years) |
6
260 m3/s |
|
GLOF |
3
000 m3/s |
|
LDOF |
5
200 m3/s |
|
Probable
Maximum Flood |
9
800 m3/s |
|
3.
Sedimentology
|
|
|
Sediment
inflow |
9.8
million m3/year |
|
Active
storage loss after 50 years |
7% |
|
Active
storage loss after 100 years |
13% |
|
4.
Diversion System |
|
|
Design
Flood |
3
070 m3/s |
|
Tunnel
section, lining |
Horseshoe
exc., inner circular concrete lining |
|
Number
of tunnel |
2 |
|
Diameter |
12 m |
|
Lengths |
|
|
Crest
Elevation of U/S Cofferdam |
El.
357 masl |
|
Crest
Elevation of D/S Cofferdam |
El.
332.50 masl |
|
5.
Dam |
|
|
Type |
Concrete
double curvature arch |
|
Crest
Level |
El.
542masl + 1.1m u/s parapet |
|
Maximum
Height (above dam foundation) |
263
m |
|
Crest
Length / Width at base/ at crest |
760
m / 80m / 8m |
|
Upstream
and Downstream Slopes |
Variable |
|
Construction
materials: |
|
|
Conventional Vibrated Concrete (CVC) |
1.92
million m3 |
|
Roller Compacted Concrete (RCC) |
3.84
million m3 |
|
Total
Concrete Volume |
5.75
million m3 |
|
6.
Spillway |
|
|
Type |
Orifice
gated spillway with flip bucket |
|
Number
of bays |
6 |
|
Bay
dimensions |
Width
5.6 m – Height 8.4 m |
|
Crest
Level |
1 at
El.515 masl / 2 at El.495 masl |
|
Design
Flood (Routed) |
6
280 m3/s for PMF, |
|
Gate
Type |
Radial
gate with hydraulic hoists |
|
Gate
size |
5.6
m x 8.4m, Six gates |
|
7.
Waterway and Powerhouse |
|
|
Intake
structures |
Bell
mouth intake structures close to the dam on the left abutment |
|
Total
Rated discharge |
6x112=672
m3/s |
|
Number
of intake |
6 |
|
Invert
Level of Intake |
El.
450masl |
|
Gate
Size- Stoplog and wheelgate |
Span
= 4 m / Height = 6m |
|
Headrace
Tunnel HRT: |
|
|
Number of HRT |
6 |
|
Intake Tunnels |
Ø 6m |
|
Headrace Tunnels |
Ø
5.3m circular |
|
Pressure Shaft |
Ø
5.3m circular |
|
Penstock |
Ø
5.3m circular |
|
Powerhouse
and transformer building |
Type:
Outdoor in the left bank |
|
Width,
Length and Height |
W 40
m x L 185 m x H 40 m |
|
GIS
building and potyard |
Adjacent
PH on platform at El.342 |
|
Width,
Length and Height |
W 60
m x L 112 m x H 15 m |
|
8.
Generating Equipment |
|
|
Turbine: |
|
|
Type |
Francis
Type, vertical axis, |
|
Number
of units in final stage |
6 |
|
Net
Head at Rated Water Level |
200
m |
|
Rated
Discharge in finale stage |
6 x
112 = 672 m3/s |
|
Installed
Capacity |
6 x
200 MW = 1 200 MW |
|
Mean
Annual Energy |
3
383 GWh (see note at the end of this table) |
|
Winter
dry season Energy |
1
408 GWh (see note at the end of this table) |
|
Summer
wet season Energy |
1
975 GWh (see note at the end of this table) |
|
Firm
Power during dry season |
from
1 200 MW 8h/day in Dec. |
|
Firm
Power during wet season |
from
918 MW 7h/day in June. |
|
Turbine
Rated Speed |
230.8
rpm |
|
Normal
Tailwater level with 6 units in operation |
El.
323.30 masl |
|
Generator: |
|
|
Type |
Vertical
shaft revolving |
|
Capacity in final stage |
6 x
235 MVA = 1 410 MVA |
|
9.
Transmission Lines |
|
|
Number |
2 |
|
Voltage |
400
kV |
|
Circuit |
Double
circuit |
|
Conductor |
Quad
Bundle MOOSE |
|
Length
BG HPP to Naubise |
40.3
km |
|
Length
BG HPP to Hetauda |
58.7
km |
|
10.
Substations |
|
|
Number |
2 |
|
Location |
1 in
Naubise and 1 in Hetauda |
|
11.
Costs |
|
|
Total
Capital cost |
2
593 MUSD |
|
12.
Economic & Financial parameters |
|
|
Economical
Internal Rate of Return EIRR |
Generation
Sc N°1 Sc N°2 |
|
Financial
Internal Rate of Return FIRR |
Generation
Sc N°1 Sc N°2 |
|
Average
energy cost |
US¢
6.4/kWh |
|
Capital
recovery period |
11
years |
|
Energy
Tariff |
Generation
Sc N°1 Sc N°2 US¢/kWh 9 7 |
|
13.
Benefits |
|
|
Energy
sales from Budhi Gandaki HPP Downstream flood reduction |
see
12. Discharge +50% from Jan. To May |
|
14.
Manpower requirement |
|
|
Foreign |
300 |