Budhi Gandaki Hydropower Project



Introduction

Budhi Gandaki Hydropower Project is a storage type project located in Central/ Western Development redy in late 70's. In 1984, a prefeasibility study of the project was prepared. The ongoing Feasibility studgion on the Budhi Gandaki River of Nepal. This project was identified during the Gandaki Basin Stuy of the Project has recommended 1200 MW capacity plant with FSL 540 masl.

Location And Access

The project is located in the Gorkha and Dading districts of the Western/Central Development Region of Nepal. The project site is accessible via Benighat on the Prithvi Highway (Kathmandu-Pokhara) (approximately 80 km from Kathmandu). From Benigat, you can cross the Trishuli River using a passable compound bridge to reach the dam and power station. Both are located about 1.5 km from the road start. 

Catchment Area:


Gorkha: 2,700 km2

Dhading: 900 km2

Nuwakot: 35 km2

China: 1,365 km2

Total: 5,000 km2

Dam Site:

About 2 km u/s of the confluence between Budhigandaki and Trhshuli at Benighat.

VDC lies in Catchment Area:

Gorkha: 37

Dhading: 27

Nuwakot: 2

Manang: 1

Total: 67

Dam Site:

Ghyalchok VDC (Gorkha)

Salang VDC (Dhading)

Silence features

1. Reservoir

Full Supply Level (FSL)

El. 540 masl

Maximum Flood Water Level

El. 542 masl

Reservoir upper boundary incl. 3m freeboard

El. 545 masl

Minimum Operating Level (MOL)

El. 496 masl

Minimum Operating Level Ultimate (MOL.ult.)

El. 467 masl

Minimum Reservoir Level (MRL)

El. 440 masl

Reservoir Bottom Level

El. 326 masl

Gross Capacity (at FSL)

4 467 Mm3

Active storage between FSL and MOL

2 226 Mm3

Reserve Live Storage between MOL and MOL.ult.

952 Mm3

Conservation volume between MOL.ult. and MRL

582 Mm3

Dead Storage between MRL and reservoir bottom

708 Mm3

Surface Area (at FSL)

63 km²

Surface Area (at MOL)

39 km2

2. Hydrology

Catchment Area

5 005 km2

Long Term Average Flow

222 m3/s (see note at the end of this table)

Construction Flood (20 years)

3 070 m3/s

Design Flood Discharge (10 000 years)

6 260 m3/s

GLOF

3 000 m3/s

LDOF

5 200 m3/s

Probable Maximum Flood

9 800 m3/s

3. Sedimentology

Sediment inflow

9.8 million m3/year

Active storage loss after 50 years

7%

Active storage loss after 100 years

13%

4. Diversion System

Design Flood

3 070 m3/s

Tunnel section, lining

Horseshoe exc., inner circular concrete lining

Number of tunnel

2

Diameter

12 m

Lengths
DT N°1
DT N°2

 
408m
438m

Crest Elevation of U/S Cofferdam

El. 357 masl

Crest Elevation of D/S Cofferdam

El. 332.50 masl

5. Dam

Type

Concrete double curvature arch

Crest Level

El. 542masl + 1.1m u/s parapet

Maximum Height (above dam foundation)

263 m

Crest Length / Width at base/ at crest

760 m / 80m / 8m

Upstream and Downstream Slopes

Variable

Construction materials:

 

   Conventional Vibrated Concrete (CVC)

1.92 million m3

   Roller Compacted Concrete (RCC)

3.84 million m3

Total Concrete Volume

5.75 million m3

6. Spillway

Type

Orifice gated spillway with flip bucket

Number of bays

6

Bay dimensions

Width 5.6 m – Height 8.4 m

Crest Level

1 at El.515 masl / 2 at El.495 masl
2 at El.470 masl / 1 at El.460 masl

Design Flood (Routed)

6 280 m3/s for PMF,
4 690 m3/s for Q10000

Gate Type

Radial gate with hydraulic hoists

Gate size

5.6 m x 8.4m, Six gates

7. Waterway and Powerhouse

Intake structures

Bell mouth intake structures close to the dam on the left abutment

Total Rated discharge

6x112=672 m3/s

Number of intake

6

Invert Level of Intake

El. 450masl
HRT invert level at El.455.60masl

Gate Size- Stoplog and wheelgate

Span = 4 m / Height = 6m

Headrace Tunnel HRT:

 

   Number of HRT

6

   Intake Tunnels

Ø 6m
Concrete lined circular
107m Horseshoe Exc. Section

   Headrace Tunnels

Ø 5.3m circular
Steel lined 22mm From 87m for Unit 6 to 165m for Unit 1
Horseshoe Exc. Section

   Pressure Shaft

Ø 5.3m circular
Steel lined 28 to 45mm
140m high
Circular Section

   Penstock

Ø 5.3m circular
Steel lined 45mm
From 352m (unit 6) to 365m (unit 1) Horseshoe Exc. Section

Powerhouse and transformer building

Type: Outdoor in the left bank

Width, Length and Height

W 40 m x L 185 m x H 40 m

GIS building and potyard

Adjacent PH on platform at El.342

Width, Length and Height

W 60 m x L 112 m x H 15 m

8. Generating Equipment

Turbine:

 

Type

Francis Type, vertical axis,

Number of units in final stage

6

Net Head at Rated Water Level

200 m

Rated Discharge in finale stage

6 x 112 = 672 m3/s

Installed Capacity

6 x 200 MW = 1 200 MW

Mean Annual Energy
(Generation Scenario N°1)

3 383 GWh (see note at the end of this table)

Winter dry season Energy
(Generation Scenario N°1)

1 408 GWh (see note at the end of this table)

Summer wet season Energy
(Generation Scenario N°1)

1 975 GWh (see note at the end of this table)

Firm Power during dry season

from 1 200 MW 8h/day in Dec.
to 934 MW 9h/day May

Firm Power during wet season

from 918 MW 7h/day in June.
to 928 MW 4h/day Nov.

Turbine Rated Speed

230.8 rpm

Normal Tailwater level with 6 units in operation

El. 323.30 masl

Generator:

 

   Type

Vertical shaft revolving

   Capacity in final stage

6 x 235 MVA = 1 410 MVA

9. Transmission Lines

Number

2

Voltage

400 kV

Circuit

Double circuit

Conductor

Quad Bundle MOOSE

Length BG HPP to Naubise

40.3 km

Length BG HPP to Hetauda

58.7 km

10. Substations

Number

2

Location

1 in Naubise and 1 in Hetauda

11. Costs

 

Total Capital cost
   Environmental and Social Cost
   Civil Works
   HEM and E&M
   HV lines
   Infrastructures and roads
   Engineering and Administration

2 593 MUSD
612 MUSD
1 265 MUSD
571 MUSD
33 MUSD
55 MUSD
57 MUSD

12. Economic & Financial parameters

 

Economical Internal Rate of Return EIRR
Unchanged for Low, Medium and High load demand forecast (In nominal term)

Generation Sc N°1 Sc N°2
15.5% 16.9%
(See note at the end of this table)

Financial Internal Rate of Return FIRR
For medium demand forecast

Generation Sc N°1 Sc N°2
7.0% 8.6%

Average energy cost

US¢ 6.4/kWh

Capital recovery period

11 years

Energy Tariff
For financing with
80% soft loan at 2% and 20% equity
100% Public Dev. and Return on Equity 10%: Mixed Public/Pvt Dev. and Return on Equity 20%:

Generation Sc N°1 Sc N°2 US¢/kWh 9 7
US¢/kWh 14.5 11.5

13. Benefits

 

Energy sales from Budhi Gandaki HPP Downstream flood reduction
Downstream increase of mean dry season flow of
Naranyani river at Devghat and Gandaki Barrage

see 12. Discharge +50% from Jan. To May

14. Manpower requirement

 

Foreign
Skilled
Semi-skilled
Unskilled
Total (persons)

300
570
1 140
3 990
6 000

 

Budi Gandaki runoff at the dam site during the last 5 years (2010-2015) and the recent By measuring the discharge at the Arughat gauge and the discharge at the dam site (see also section 2.1).

Consultants estimate that streamflow at the dam site is likely to be 26% higher than predicted by the hydrological studies in the feasibility report. Parallel measurements have been available for years, according to feasibility reports.

An increase in river flow at this dam site will directly impact the annual production of BG HPP, referred to as Production Scenario #2. This is 26% higher. H. 4,250 GWh per year (1,620 GWh in dry season or 10.8 GWh/day with guaranteed capacity between 970 and 1200 MW).

The consultants believe that five years of parallel flow measurements at the Arughat dam site are sufficient to give the new practice a reasonable level of confidence, but additional projects are needed to expand the database and additional projects. It is recommended to continue measurements at the dam site. Fully supporting generational possibilities. 
Amit Bhandari

Hi, i am Amit Bhandari from Nepal. I am here for showing my hidden views about objects through words.

Post a Comment

Previous Post Next Post